doe-o-413-3

Knowledge base from the DOE Order on Program and Project Management for the Acquisition of Capital Assets (DOE O 413.3 series). Use for Critical Decisions CD-0–CD-4, performance baselines, acquisition

SKILL.md

GitHub
<!-- argument-hint: [topic, CD, or chapter number] -->

DOE Capital Asset Project Management (O 413.3 series)

Source: DOE O 413.3C (2026-08-05; cancels O 413.3B Chg 7) (US Government work, public domain) | Chapters: 6

When to use

Reach for this pack when planning, governing, or reviewing DOE/NNSA capital asset projects under the 413.3 Order family — mission need through completion, Critical Decision gates, performance baselines, acquisition strategy and IPTs, EVMS/PARS reporting, risk-informed approvals, exemptions, and contractor requirements flow-down.

Prerequisites: none — plain Markdown; no MCP server, API key, or licence tier needed at runtime.

How to Use This Skill

  • Without arguments — load the core frameworks below.
  • With a topic — ask about CD-0–CD-4, PB, EVMS, IPT, PARS, risk, exemptions, or CRD.
  • With a chapter — ask for ch01 through ch06.

Supporting files: glossary.md, patterns.md, cheatsheet.md.

Core Frameworks & Mental Models

What the Order is

Risk-informed direction for acquiring capital assets so projects meet the original performance baseline and mission/ES&H/security performance unless a directed change intervenes — aligned with OMB capital-programming expectations.

Critical Decision spine

CD-0 mission need → CD-1 alternative and cost range → CD-2 performance baseline → CD-3 execution/construction start → CD-4 operations/completion.

Control triad after CD-2

Control Role
Performance baseline Commitment snapshot (scope/cost/schedule)
Change control Authorized evolution of the baseline
EVMS + PARS Performance measurement and Department visibility

Governance web

Line management owns outcomes; PSO/PMSO/PM/FPD/IPT and approval authorities form the decision system; CRD carries requirements to contractors; reviews provide independent signal.

Chapter Index

# Section Key content
ch01 Purpose, Applicability, Governance Scope, thresholds, OMB links, exemptions, cancellation
ch02 Critical Decisions CD-0–CD-4 Gate intents, products, authorities
ch03 Acquisition Planning and IPT Strategy, PEP, IPT, front-end planning
ch04 Baseline, Cost, Schedule, EV PB, estimates, EVMS, PARS
ch05 Risk, Safety, Exceptions Risk-informed decisions, S&S/nuclear interfaces, exemptions
ch06 Reviews, Responsibilities, CRD Oversight, roles, contractor flow-down, closeout

Topic Index

  • Acquisition strategy → ch03
  • AoA / alternatives → ch02, ch03
  • CD-0 mission need → ch02
  • CD-1 cost range → ch02
  • CD-2 performance baseline → ch02, ch04
  • CD-3 construction/execution → ch02
  • CD-4 completion/operations → ch02, ch06
  • Change control → ch04
  • Contingency / management reserve → ch04, ch05
  • CRD / contractors → ch01, ch06
  • EVMS → ch04
  • Exemptions / equivalencies → ch01, ch05
  • FPD / IPT → ch03, ch06
  • PARS → ch01, ch04
  • Project reviews → ch06
  • Risk management → ch05
  • TPC thresholds → ch01, ch02

Supporting Files

  • glossary.md — capital-asset PM terms with chapter references
  • patterns.md — implementation patterns (When/How/Trade-offs)
  • cheatsheet.md — CD table, control stack, tells and smells

Scope & Limits

This pack covers the DOE Order on Program and Project Management for the Acquisition of Capital Assets using the consolidated current Order PDF at build time: DOE O 413.3C (approved 2026-08-05), which cancels DOE O 413.3B Chg 7 (2023-06-21). Extract metadata source_pages=132. Pack slug doe-o-413-3 (renamed from doe-413-3b at v1.17.x; catalog carries the old slug as an alias) tracks the current Order series. It does not replace site implementing procedures, full text of companion G 413.3 guides, nuclear safety rule detail (e.g., 10 CFR 830), or GAO-grade estimating standards. In-PDF third-party copyright check at build found no copyright notices. US Government public domain work. No source-material download link is published.