coordination-log

Keeps one dated log of conflicts between disciplines and follows each to the only ending that counts: both sets showing the same thing. Records which two documents disagree, what each says, who resolv

SKILL.md

GitHub

Coordination Log

A conflict is found, discussed, and agreed. Then one discipline revises and the other does not, and the set goes out still disagreeing with itself. The agreement was never the deliverable; two drawings showing the same thing is.

Scope and limits — read first

What this does. Consolidates conflicts from every discipline review into one log, keeps both parties' values rather than one, and tracks each to closure — which means verified in both sets at a stated revision.

What this does not do.

  • It holds no positions. It does not decide which discipline is right. The conflicts come from the review skills and the resolutions from the people who own them.
  • It does not find conflicts. mep-review, structural-drawing-review, civil-drawing-review, penetration-review and design-ceiling each read one relationship; this holds what they produce.
  • It does not run clash detection or open a model.
  • It does not replace project-tracker, which holds issues, decisions and risks generally. A coordination conflict has a shape that log does not carry: two documents, two values, and a closure that has to be checked twice.
  • It does not track RFIs or changes. rfi-tracker and change-order-tracker do, and this records where a conflict became one.
  • It does not replace the Architect of Record.

What you need before starting. The reviews that have been run and their output. Which disciplines are on the project and who leads each. The issue and revision dates of each set. The next issue date.

Workflow

Step 1. Establish the sets and the rhythm

Ask, in one message:

  1. Which disciplines, who leads each, and how are they reached?
  2. What is the current revision of each set, and its date?
  3. Which reviews have been run, and do you have their output?
  4. What is the next issue, and what has to be closed before it?
  5. Is there a coordination meeting, and how often?
  6. Is there a model, federated or otherwise, and does anyone run clash detection on it?

Record each set's revision. A conflict logged against one revision and checked against another is a conflict nobody closed.

Step 2. Log each conflict with both values

# Conflict Set A A says Set B B says Found by Raised Owner Status

Both values, always. A log recording only "duct clashes with beam" loses the information needed to check the fix. Record the dimension, the level, the sheet and the location on each side.

Status is one of: open, with owner, resolved not drawn, drawn one set, drawn both sets, closed, accepted as is.

resolved not drawn and drawn one set are the two that matter. Everything gets to resolved in a meeting; most of the failures live in the gap between that and both sets being revised. Report their count first in every read-back.

accepted as is is a legitimate ending and it needs a name and a date against it, because it will be questioned later.

Step 3. Give each conflict one owner and one resolver

Two different roles and they get confused:

  • Owner. Who chases it. One name.
  • Resolver. Which discipline has to change something, and often it is both.

Where the resolver is "both", the conflict has two closures and neither is done until the other is. Log them as one row with two closure checks rather than as two rows, so it cannot be half-closed.

A conflict with two owners has none.

Step 4. Close only against a revision, in both sets

Closure is a check, not a report:

# Resolution Set A revision showing it Set B revision showing it Verified by Date

A row is closed only when both revision columns are filled and somebody's name is in verified by. Nothing else counts. A resolution agreed in a meeting, an email confirming it, or a consultant saying it is done are all resolved not drawn.

Re-check at every issue. A conflict closed at one revision can reopen when a later revision changes one set and not the other, and that reopening is invisible unless somebody looks.

Step 5. Read back

At every coordination meeting and before every issue:

  • resolved not drawn and drawn one set, first, with how long each has been there.
  • open by age, oldest first.
  • Everything with no owner.
  • Everything accepted as is, listed, so it is a decision that stays visible.
  • Conflicts that have reopened.
  • Which reviews have not been run since the last issue, because a set revised without being re-reviewed has conflicts nobody has found yet.

Report elapsed time. Never predict when something will close.

Step 6. Write the log

One dated file per project, appended to rather than rewritten. Ask where it lives on the first run and use the same path after. Every entry carries a date, a source and the revision it applies to.

Rules

  • Never take a position on which set is right.
  • Record both values on every conflict, with sheet and location on each side.
  • Log the revision of each set at the time the conflict was raised.
  • One owner per conflict, or flag that there is none.
  • closed requires both revision columns and a verifier's name. Nothing else.
  • Report resolved not drawn and drawn one set first in every read-back.
  • Re-check closed conflicts at every issue.
  • Append; never rewrite an earlier entry.

Anti-patterns

  • Logging the conflict without both values.
  • Closing on the strength of a meeting or an email.
  • Treating a consultant's word that it is fixed as verification.
  • One row per discipline for a conflict that needs both to change.
  • Losing the revision, so nobody can tell whether a fix landed before or after.
  • Letting accepted as is disappear into the closed pile.
  • Issuing a set without re-running the reviews on what changed.
  • Keeping coordination conflicts in the general issues log, where the second closure check does not exist.

Resources