critical-path-analyzer

Analyze construction schedule critical path. Identify critical activities, calculate float, simulate schedule impacts, and optimize project duration.

SKILL.md

GitHub

Critical Path Analyzer

Overview

Analyze construction schedules using Critical Path Method (CPM). Identify critical activities, calculate total and free float, simulate what-if scenarios, and find opportunities to compress schedule.

"Understanding the critical path is essential for effective schedule management" — DDC Community

CPM Concepts

┌─────────────────────────────────────────────────────────────────┐
│                    CRITICAL PATH METHOD                          │
├─────────────────────────────────────────────────────────────────┤
│                                                                  │
│  Activity A (5d)  ──→  Activity C (10d)  ──→  Activity E (3d)   │
│       ↓                                            ↑             │
│  Activity B (8d)  ──────────→  Activity D (6d)  ───┘            │
│                                                                  │
│  Critical Path: A → C → E (18 days)                             │
│  Float on B→D: 4 days                                           │
│                                                                  │
└─────────────────────────────────────────────────────────────────┘

Technical Implementation

from dataclasses import dataclass, field
from typing import List, Dict, Optional, Set, Tuple
from datetime import datetime, timedelta
from collections import defaultdict
import heapq

@dataclass
class Activity:
    id: str
    name: str
    duration: int  # days
    predecessors: List[str] = field(default_factory=list)
    successors: List[str] = field(default_factory=list)

    # Calculated values
    early_start: int = 0
    early_finish: int = 0
    late_start: int = 0
    late_finish: int = 0
    total_float: int = 0
    free_float: int = 0
    is_critical: bool = False

    # Optional attributes
    resources: List[str] = field(default_factory=list)
    cost: float = 0.0
    actual_start: Optional[datetime] = None
    actual_finish: Optional[datetime] = None
    percent_complete: float = 0.0

@dataclass
class ScheduleAnalysis:
    project_duration: int
    critical_path: List[str]
    critical_activities: List[Activity]
    near_critical_activities: List[Activity]  # Float <= threshold
    total_activities: int
    float_distribution: Dict[int, int]

class CriticalPathAnalyzer:
    """Analyze construction schedule critical path."""

    def __init__(self):
        self.activities: Dict[str, Activity] = {}
        self.analysis: Optional[ScheduleAnalysis] = None

    def add_activity(self, id: str, name: str, duration: int,
                    predecessors: List[str] = None,
                    resources: List[str] = None,
                    cost: float = 0.0) -> Activity:
        """Add activity to schedule."""
        activity = Activity(
            id=id,
            name=name,
            duration=duration,
            predecessors=predecessors or [],
            resources=resources or [],
            cost=cost
        )
        self.activities[id] = activity

        # Update successor relationships
        for pred_id in activity.predecessors:
            if pred_id in self.activities:
                self.activities[pred_id].successors.append(id)

        return activity

    def import_schedule(self, activities: List[Dict]) -> int:
        """Import activities from list of dicts."""
        count = 0
        for act in activities:
            self.add_activity(
                id=act['id'],
                name=act['name'],
                duration=act['duration'],
                predecessors=act.get('predecessors', []),
                resources=act.get('resources', []),
                cost=act.get('cost', 0)
            )
            count += 1
        return count

    def calculate_critical_path(self, near_critical_threshold: int = 5) -> ScheduleAnalysis:
        """Calculate critical path using forward and backward pass."""
        if not self.activities:
            raise ValueError("No activities to analyze")

        # Reset calculations
        for act in self.activities.values():
            act.early_start = 0
            act.early_finish = 0
            act.late_start = 0
            act.late_finish = 0
            act.total_float = 0
            act.free_float = 0
            act.is_critical = False

        # Forward pass - calculate early start/finish
        self._forward_pass()

        # Determine project duration
        project_duration = max(act.early_finish for act in self.activities.values())

        # Backward pass - calculate late start/finish
        self._backward_pass(project_duration)

        # Calculate float and identify critical activities
        critical_path = []
        critical_activities = []
        near_critical = []

        for act in self.activities.values():
            act.total_float = act.late_start - act.early_start

            # Calculate free float
            if act.successors:
                min_succ_es = min(self.activities[s].early_start for s in act.successors)
                act.free_float = min_succ_es - act.early_finish
            else:
                act.free_float = project_duration - act.early_finish

            # Identify critical (zero float)
            if act.total_float == 0:
                act.is_critical = True
                critical_activities.append(act)
            elif act.total_float <= near_critical_threshold:
                near_critical.append(act)

        # Build critical path sequence
        critical_path = self._build_critical_path_sequence(critical_activities)

        # Float distribution
        float_dist = defaultdict(int)
        for act in self.activities.values():
            float_dist[act.total_float] += 1

        self.analysis = ScheduleAnalysis(
            project_duration=project_duration,
            critical_path=critical_path,
            critical_activities=critical_activities,
            near_critical_activities=near_critical,
            total_activities=len(self.activities),
            float_distribution=dict(float_dist)
        )

        return self.analysis

    def _forward_pass(self):
        """Forward pass to calculate early start/finish."""
        # Topological sort
        in_degree = {act_id: len(act.predecessors) for act_id, act in self.activities.items()}
        queue = [act_id for act_id, degree in in_degree.items() if degree == 0]

        while queue:
            act_id = queue.pop(0)
            act = self.activities[act_id]

            # Early start is max of predecessor early finishes
            if act.predecessors:
                act.early_start = max(
                    self.activities[pred].early_finish for pred in act.predecessors
                )
            else:
                act.early_start = 0

            act.early_finish = act.early_start + act.duration

            # Process successors
            for succ_id in act.successors:
                in_degree[succ_id] -= 1
                if in_degree[succ_id] == 0:
                    queue.append(succ_id)

    def _backward_pass(self, project_duration: int):
        """Backward pass to calculate late start/finish."""
        # Start from end activities
        end_activities = [act for act in self.activities.values() if not act.successors]

        for act in end_activities:
            act.late_finish = project_duration
            act.late_start = act.late_finish - act.duration

        # Process in reverse topological order
        processed = set(act.id for act in end_activities)
        queue = list(end_activities)

        while queue:
            act = queue.pop(0)

            for pred_id in act.predecessors:
                pred = self.activities[pred_id]

                # Late finish is min of successor late starts
                new_late_finish = act.late_start
                if pred.late_finish == 0 or new_late_finish < pred.late_finish:
                    pred.late_finish = new_late_finish
                    pred.late_start = pred.late_finish - pred.duration

                # Check if all successors processed
                all_succ_processed = all(
                    s in processed for s in pred.successors
                )
                if all_succ_processed and pred_id not in processed:
                    processed.add(pred_id)
                    queue.append(pred)

    def _build_critical_path_sequence(self, critical_activities: List[Activity]) -> List[str]:
        """Build ordered critical path sequence."""
        if not critical_activities:
            return []

        # Find start of critical path (no critical predecessors)
        critical_ids = {act.id for act in critical_activities}

        start_acts = [act for act in critical_activities
                     if not any(p in critical_ids for p in act.predecessors)]

        if not start_acts:
            return [act.id for act in critical_activities]

        # Build sequence
        path = []
        current = start_acts[0]

        while current:
            path.append(current.id)
            # Find next critical successor
            critical_successors = [s for s in current.successors if s in critical_ids]
            current = self.activities[critical_successors[0]] if critical_successors else None

        return path

    def simulate_delay(self, activity_id: str, delay_days: int) -> Dict:
        """Simulate impact of delay on an activity."""
        if activity_id not in self.activities:
            raise ValueError(f"Activity {activity_id} not found")

        activity = self.activities[activity_id]
        original_duration = activity.duration

        # Temporarily modify duration
        activity.duration = original_duration + delay_days

        # Recalculate
        new_analysis = self.calculate_critical_path()

        # Restore original
        activity.duration = original_duration
        original_analysis = self.calculate_critical_path()

        impact = {
            "activity": activity_id,
            "delay_days": delay_days,
            "original_duration": self.analysis.project_duration,
            "new_duration": new_analysis.project_duration,
            "project_impact": new_analysis.project_duration - original_analysis.project_duration,
            "absorbed_by_float": delay_days <= activity.total_float,
            "new_critical_path": new_analysis.critical_path,
            "critical_path_changed": new_analysis.critical_path != original_analysis.critical_path
        }

        return impact

    def find_compression_opportunities(self, target_reduction: int) -> List[Dict]:
        """Find activities that could be crashed to reduce duration."""
        if not self.analysis:
            self.calculate_critical_path()

        opportunities = []

        for act in self.analysis.critical_activities:
            # Assume activities can be crashed by 20% max
            max_crash = int(act.duration * 0.2)
            if max_crash > 0:
                opportunities.append({
                    "activity_id": act.id,
                    "activity_name": act.name,
                    "current_duration": act.duration,
                    "max_crash_days": max_crash,
                    "crash_cost_per_day": act.cost * 0.5 / max_crash if max_crash else 0,
                    "on_critical_path": True
                })

        # Sort by crash cost
        opportunities.sort(key=lambda x: x["crash_cost_per_day"])

        return opportunities

    def get_float_report(self) -> str:
        """Generate float analysis report."""
        if not self.analysis:
            self.calculate_critical_path()

        lines = [
            "# Float Analysis Report",
            "",
            f"**Project Duration:** {self.analysis.project_duration} days",
            f"**Critical Activities:** {len(self.analysis.critical_activities)}",
            f"**Near-Critical Activities:** {len(self.analysis.near_critical_activities)}",
            "",
            "## Critical Path",
            "",
            " → ".join(self.analysis.critical_path),
            "",
            "## Activities by Float",
            "",
            "| Activity | Duration | ES | EF | LS | LF | TF | FF | Critical |",
            "|----------|----------|----|----|----|----|----|----|----------|"
        ]

        # Sort by float
        sorted_acts = sorted(self.activities.values(), key=lambda a: a.total_float)

        for act in sorted_acts:
            crit = "YES" if act.is_critical else ""
            lines.append(
                f"| {act.id} | {act.duration} | {act.early_start} | {act.early_finish} | "
                f"{act.late_start} | {act.late_finish} | {act.total_float} | {act.free_float} | {crit} |"
            )

        return "\n".join(lines)

    def generate_gantt_data(self, start_date: datetime) -> List[Dict]:
        """Generate data for Gantt chart visualization."""
        gantt_data = []

        for act in self.activities.values():
            gantt_data.append({
                "id": act.id,
                "name": act.name,
                "start": (start_date + timedelta(days=act.early_start)).isoformat(),
                "end": (start_date + timedelta(days=act.early_finish)).isoformat(),
                "duration": act.duration,
                "float": act.total_float,
                "is_critical": act.is_critical,
                "predecessors": act.predecessors,
                "progress": act.percent_complete
            })

        return gantt_data

Quick Start

# Initialize analyzer
analyzer = CriticalPathAnalyzer()

# Add activities
analyzer.add_activity("A", "Site Prep", 5)
analyzer.add_activity("B", "Foundation Excavation", 8, predecessors=["A"])
analyzer.add_activity("C", "Foundation Forms", 4, predecessors=["B"])
analyzer.add_activity("D", "Foundation Pour", 2, predecessors=["C"])
analyzer.add_activity("E", "Foundation Cure", 7, predecessors=["D"])
analyzer.add_activity("F", "Steel Erection", 15, predecessors=["E"])
analyzer.add_activity("G", "MEP Rough-in", 20, predecessors=["F"])
analyzer.add_activity("H", "Exterior Envelope", 25, predecessors=["F"])
analyzer.add_activity("I", "Interior Finishes", 30, predecessors=["G", "H"])
analyzer.add_activity("J", "Final Inspection", 3, predecessors=["I"])

# Calculate critical path
analysis = analyzer.calculate_critical_path()

print(f"Project Duration: {analysis.project_duration} days")
print(f"Critical Path: {' → '.join(analysis.critical_path)}")
print(f"Critical Activities: {len(analysis.critical_activities)}")

# Simulate delay
impact = analyzer.simulate_delay("F", 5)
print(f"\nDelay Impact: {impact['project_impact']} days")
print(f"Absorbed by Float: {impact['absorbed_by_float']}")

# Find compression opportunities
opportunities = analyzer.find_compression_opportunities(10)
for opp in opportunities[:3]:
    print(f"Crash {opp['activity_name']}: up to {opp['max_crash_days']} days")

# Generate report
print(analyzer.get_float_report())

Requirements

pip install (no external dependencies)