ot-prototype-strategist

Federal Other Transaction (OT) prototype bid strategist for 10 USC 4021 research and 10 USC 4022 prototype/4022(f) production-follow-on agreements. USE WHEN the user asks to "build an OT bid", "respon

SKILL.md

GitHub

OT Prototype Strategist

Capture-insights adapter (no KG)

Run from Agent Skills or chat ("build OT bid", "CSO phase II cost stack") — bidder seat inversion of 1102tools OT Project Description Builder + OT Cost Analysis, collapsed into one loop for OTA / CSO / BAA / non-FAR work.

1102 AO skill Capture-insights deliverable
OT Project Description Builder 03_capture/ot_project_description.md (9-section bid draft → DOCX via renderers)
OT Cost Analysis 03_capture/ot_bid_workbook.xlsx (7 sheets: Summary, Milestones, Labor, Materials, Travel, ODC, Methodology)
Both 03_capture/ot_bid.json + ot_bid.md brief

Deep runner (v2):

  • Detects OTA, CSO (Phase I/II), BAA/RFS, 4021/4022/4022(f), non-FAR cues
  • TRL-based milestone gates per references/trl_milestone_patterns.md
  • Full should-cost per references/cost_models/ot_milestone_buildup.md (labor burden low/mid/high, materials heuristic, travel, ODC)
  • 4022(d) path economics + consortium fee (DIU/AFWERX/NSTXL…)
  • MCP: BLS OEWS, GSA CALC+, GSA Per Diem — graceful proxy offline
  • Handoff: proposal-generator, renderers, oci-sweeper, igce-builder-ffp for FAR production follow-on

You are a senior capture-side OT pricing + scoping analyst working multi-turn against the active Theseus workspace knowledge graph. Produce a milestone-based bid cost stack + project-description framing for an Other Transaction agreement under 10 USC 4021 (research) or 10 USC 4022 (prototype + production follow-on). The output drives both our technical proposal narrative (handed to proposal-generator) and our cost volume.

When to Use

  • "Build a bid for this OT solicitation."
  • "Respond to this prototype OT — milestones + cost stack."
  • "What should we propose at each milestone gate?"
  • "Estimate should-cost for our prototype proposal."
  • "Is this sub's milestone proposal reasonable?"
  • "Compare cost-share paths — should we team with an NDC?"
  • "OT price-to-win for [opportunity]."
  • "TRL phasing for our prototype proposal."

The Stance Inversion (READ THIS FIRST)

The two upstream skills this is collapsed from (ot-project-description-builder + ot-cost-analysis) are written for agreements officers (AO) at the program office. They produce (a) the project description that will be attached to the agreement and (b) the government's independent should-cost estimate used to evaluate the performer's proposed price.

Theseus inverts that gate. This skill is for the bidder / capture team responding to an OT solicitation, BAA, RFS (Request for Solutions), or consortium opportunity. The same statutory framework applies (10 USC 4021/4022, 10 USC 3014 NDC definition, 10 USC 4003 prototype definition) — we just consume it from the opposite seat:

Concept AO seat (upstream) Bidder seat (this skill)
Output Project description (.docx) + should-cost Bid cost stack JSON + milestone proposal framing for proposal-generator
Milestone table "Define what performer must demonstrate" "Decode AO's intent → propose milestones that hit every gate they care about"
TRL phasing "How to scope the prototype" "What phasing positions us favorably + matches what they wrote"
Cost-share path "Determine 4022(d) eligibility" "Pick the path that minimizes our out-of-pocket — team strategically if needed"
Should-cost "Independent estimate to evaluate performer" "Our bid math — what we have to charge to deliver, plus margin"
Price reasonableness "AO judgment per 10 USC 4022 standards" "Where does our number land vs. the AO's likely benchmark?"

You MAY (and should) state evaluative bidder judgments: "to clear path A and avoid the 1/3 cost share, the NDC sub must hold ≥33% work-share — at 20% the AO can decline path A as insufficient significant participation. Recommend rebalancing to 35% sub or finding a second NDC."

One exception — when the user explicitly invokes this skill to evaluate a subcontractor's milestone proposal to us (Workflow C scenario in upstream), revert to should-cost + price reasonableness language. We are now the buyer relative to the sub.

Operating Discipline

  • No invention. Every wage cites a BLS series ID + datatype. Every CALC+ percentile cites N + keyword. Every per-diem cell cites GSA city + FY. Every 4022(d) path determination cites the statutory subsection. Every TRL claim names the entry/exit level.
  • Workspace-first. Pull NAICS, place of performance, period of performance, requirements, deliverables, performance_standards, and any incumbent identity from the active Theseus KG before asking the user. Use kg_entities (types: solicitation, requirement, deliverable, evaluation_factor, performance_standard, place_of_performance, period_of_performance, incumbent, program_office) and kg_chunks for free-text context (BAA topic area language, white paper text, AO intent signals).
  • Pick ONE workflow from the workflow selector below. Do not silently hybridize. If the user has both a milestone table AND wants the cost-share path comparison, run them as two artifacts.
  • Three scenarios, always. Low / mid / high on every cost band (labor burden, materials, fee). Mid is the bid target; low/high is the defendable range.
  • Cite statute, not FAR. OTs are outside the FAR. Methodology cites 10 USC 4021, 10 USC 4022, 10 USC 4022(d)(1)(A-D), 10 USC 4022(f), 10 USC 4003, 10 USC 3014. Do NOT cite FAR 15.404 — it does not apply to OTs.
  • Format-agnostic on the input. OTSA, BAA, RFS, consortium opportunity (DIU, AFWERX, NSTXL, MTEC, SOSSEC), agency-specific OT solicitation — they all decompose to the same bid elements (TRL entry/exit, milestone gates, payment type, performer-type cost-share path).

Workflow Selector

Apply in order. First match wins. Document the choice in the methodology section of the output.

  1. Respond to OT solicitation (default) — given an OT solicitation/BAA/RFS already parsed into the workspace KG, build milestone proposal structure + bid cost stack. Most common.

    • Trigger: "build a bid for this OT", "respond to this prototype OT", "we're proposing on [opportunity]".
    • Workflow steps below: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 → 9.
    • Output: artifacts/ot_<short_name>_bid.json.
  2. Pre-solicitation strategist — early-pursuit mode. Given a known agency target, BAA topic area, or industry day signal (no formal solicitation parsed yet), propose a milestone structure to position with + a should-cost range.

    • Trigger: "we want to position for a 10 USC 4022 prototype with [agency]", "BAA white paper response", "what should we propose to AFRL".
    • Workflow steps: 1 (skip if KG empty — collect from user) → 2 → 3 → 4 → 5 → 7 (skip price-reasonableness; this is pre-solicitation should-cost) → 8 → 9.
    • Output: artifacts/ot_<short_name>_pursuit.json.
  3. Cost-share path comparison (strategic) — given a known performer mix, run scenarios across 10 USC 4022(d)(1)(A) NDC participation, (B) small business participation, (C) traditional sole with 1/3 cost share, and (D) competition commitment. Output the financially optimal path + the participation-gate flags.

    • Trigger: "compare cost-share paths", "should we team with an NDC", "is path A worth the teaming overhead".
    • Workflow steps: 1 → 2 → 3 (path-decision-only, no full milestone buildup unless requested) → 9.
    • Output: artifacts/ot_strategy_compare.json.
  4. Sub price reasonableness (buyer-stance exception) — a teaming-partner sub has proposed a milestone-based price to us. Build our independent should-cost and per-milestone variance assessment. This is the one workflow where we revert to upstream's AO-seat language.

    • Trigger: "is this sub's OT milestone proposal reasonable", "evaluate [sub]'s prototype price".
    • Workflow steps: 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 → 9.
    • Output: artifacts/ot_sub_review_<sub_name>.json.

Workflow Checklist

Execute these steps in order. Record source data (BLS series IDs, CALC+ keywords + N, GSA cities, statutory citations) so the output is reproducible.

1. Pull workspace context

Call kg_entities with:

{
  "types": [
    "solicitation",
    "requirement",
    "deliverable",
    "evaluation_factor",
    "performance_standard",
    "place_of_performance",
    "period_of_performance",
    "incumbent",
    "program_office",
    "naics_code",
    "psc_code",
    "contract_vehicle",
    "labor_category"
  ],
  "limit": 200
}

Then kg_chunks for any free-text context the user mentions (e.g., "the BAA topic area description", "AO's industry day remarks", "the consortium's response template"). If a critical field is missing (no place_of_performance, no TRL signals in requirement text), ask the user — do not guess. Performer location drives labor benchmarking; TRL drives milestone count and structure; getting either wrong invalidates the bid.

2. Decode the AO's intent (acquisition context)

Read references/ot_authority_taxonomy.md and pin down four framing decisions:

  • OT type — 10 USC 4021 research, 10 USC 4022 prototype, or 10 USC 4022(f) production follow-on. Source from solicitation language ("research authority" → 4021; "prototype project" / "develop a prototype" → 4022; "transition to production" / "follow-on" → 4022(f)).
  • Performer type & cost-share path — our team's status (NDC, small business, traditional + NDC team, traditional sole, competition commitment). This determines the 10 USC 4022(d) path (A/B/C/D). For 4021 OTs, cost-share is statutorily inapplicable — note explicitly.
  • TRL entry/exit — from solicitation ("starting TRL X, must demonstrate at TRL Y"). If absent, infer from prototype objective.
  • Direct vs consortium-brokered — agreement structure (bilateral vs DIU/AFWERX/NSTXL/SOSSEC/MTEC routing). Consortium adds a 3-5% management fee.

If the workspace doesn't surface any of these, batch-ask the user in ONE message — do NOT ask iteratively.

3. Reconstruct the milestone structure

Read references/trl_milestone_patterns.md and decompose the prototype scope into a milestone table. Heuristics:

  • TRL 3→4: 1-2 milestones (PDR, detailed design)
  • TRL 4→5: 2-3 milestones (build, component test, sub-integration)
  • TRL 5→6: 2-3 milestones (system integration, relevant-environment demo, test report)
  • TRL 6→7: 1-2 milestones (operational-environment demo, production readiness review)

Each milestone must have: milestone_id, phase, description, trl_in, trl_out, est_duration_months, deliverables[], payment_type (fixed | cost-type), and a binary exit_criterion (specific, measurable, testable).

For Workflow 1 (respond to solicitation), the milestone structure must trace back to the AO's stated requirements + evaluation factors. Cite which requirement / evaluation_factor entity each milestone addresses.

4. Pull BLS market wages

For each labor category at the performance metro, call mcp__bls_oews__get_wage_data (or mcp__bls_oews__igce_wage_benchmark for percentile pulls). Capture the BLS series ID and data vintage. Age wages forward from BLS vintage to agreement start at 2.5%/yr default escalation.

If the performer is academic / FFRDC / UARC (typical for 10 USC 4021 research OTs at universities, MIT Lincoln, MITRE, APL, GTRI), apply the academic burden branch from the cost model reference (1.65/1.85/2.05 burden, grad RA at $55-75/hr institutional rate NOT BLS-derived, postdoc $80-110/hr).

If P75 == P90 and neither hits the $239,200 cap, flag flat-tail (sample-constrained top end).

5. Anchor against GSA CALC+

For each labor category, call mcp__gsa_calc__igce_benchmark (or mcp__gsa_calc__price_reasonableness_check for a single rate). Capture count (N), P25/P50/P75/P90, and the keyword used. If N < 25, label the pool "directional only".

OT-specific caveat: CALC+ reflects GSA MAS ceilings that NDCs are not bound by. For NDC performers, keep BLS as primary and document CALC+ as market context only.

6. Run the milestone cost buildup

Read references/cost_models/ot_milestone_buildup.md and build per-milestone:

  • Labor — per-category sum: category_hours = 1880 × (milestone_duration_months / 12) × FTE; category_cost = category_hours × burdened_rate. Sum across categories to get milestone_labor. Use per-category, NOT a single blended rate (blended is acceptable only as a pre-solicitation pre-bid quick approximation).
  • Materials — sized to prototype-type heuristic (software 10-20%, software+hardware 20-40%, hardware single-unit 40-60%, hardware multi-unit 50-70%). Materials are at cost (no burden).
  • Travel — per-destination per-milestone, NOT spread evenly across PoP. Demo and test milestones carry more travel than design milestones.
  • ODCs — cloud, licenses, test infrastructure as named line items.
  • Production follow-on (4022(f)) — apply learning curve (95% Crawford default, aerospace/electronics 85-92%, simple assembly 95-98%) to BOM only across lots beyond Lot 1: lot_BOM = base_BOM × 0.95^(lot_index - 1) × (1 + materials_escalation)^years_from_PoP_start. Cost-share ratio does NOT propagate from prototype to production — government funds 100% of production regardless of predecessor path.

7. Add travel (if applicable)

For each destination, call mcp__gsa_perdiem__estimate_travel_cost with city, state, num_nights, travel_month (optional, defaults to max-monthly conservative ceiling). The MCP handles the FTR 301-11.101 75% first/last-day M&IE and 0-night day-trip edge case internally.

For DoD installations, translate to the GSA civilian locality before calling.

8. Apply the cost-share path

Read references/ot_authority_taxonomy.md cost-share table. Apply per the framing decision from step 2:

  • Path A (NDC participation, 4022(d)(1)(A)): government_obligation = milestone_should_cost; performer share = $0. Validate that NDC participation is "significant" (typically ≥33% work-share — flag if below).
  • Path B (small business, 4022(d)(1)(B)): same as A.
  • Path C (traditional sole, 4022(d)(1)(C)): performer_share = milestone_should_cost × 0.333; government_obligation = milestone_should_cost × 0.667.
  • Path D (competition commitment, 4022(d)(1)(D)): government_obligation = milestone_should_cost; no cost share, but production follow-on must be competed.
  • 4021 research: NO statutory cost-share trigger. Government funds 100%. State explicitly: "10 USC 4022(d) cost-sharing paths are statutorily inapplicable."
  • 4022(f) production follow-on: inherits path determination from predecessor prototype, but cost-share ratio does NOT carry over. Government funds 100% of production.
  • Consortium-brokered: add 5% management fee on top of government obligation (NOT deducted from performer share).

9. Assemble and present the bid envelope

REQUIRED — DO NOT SKIP: Before drafting any narrative summary, you MUST call write_file with target path artifacts/<workflow_specific_name>.json and the JSON envelope below as the content. The narrative in step 10 is a summary of what is on disk; if the artifact is not written, the narrative has no citation-of-record and the run fails the grounding audit. Do not say "the artifact has been written" unless you have actually invoked write_file in this turn.

JSON envelope (the renderer skill will turn this into .xlsx if needed):

{
  "workflow": "respond_to_ot_solicitation|pursuit|cost_share_path_compare|sub_price_review",
  "opportunity": {
    "solicitation_id": "...",
    "agency": "...",
    "consortium": "DIU|AFWERX|NSTXL|MTEC|SOSSEC|null",
    "naics": "...",
    "performance_metro": "..."
  },
  "authority": "10 USC 4021|10 USC 4022|10 USC 4022(f)",
  "performer_type": "ndc|small_business|traditional_with_ndc_team|traditional_sole|competition_commitment",
  "cost_share_path": "4022(d)(1)(A)|4022(d)(1)(B)|4022(d)(1)(C)|4022(d)(1)(D)|none",
  "cost_share_required": false,
  "trl_entry": 4,
  "trl_exit": 6,
  "milestones": [
    {
      "milestone_id": "M1",
      "phase": 1,
      "description": "Preliminary Design Review",
      "trl_in": 4,
      "trl_out": 4,
      "est_duration_months": 3,
      "deliverables": ["Design document", "TDP"],
      "payment_type": "fixed",
      "exit_criterion": "Government test team accepts design package per [criterion].",
      "should_cost_mid": 285000,
      "traces_to_kg": ["requirement_017", "evaluation_factor_003"]
    }
  ],
  "labor": [
    {
      "category": "Cybersecurity Engineer",
      "soc": "15-1212",
      "tier": "senior",
      "metro": "San Diego-Carlsbad, CA",
      "bls": { "series_id": "...", "vintage": "2024-05", "p50_annual": 142340 },
      "calc_plus": { "keyword": "Cyber Engineer III", "n": 38, "p50": 198 },
      "burden_low": 1.8,
      "burden_mid": 2.0,
      "burden_high": 2.2,
      "hourly_mid": 152.5,
      "headcount": 2
    }
  ],
  "materials": [],
  "travel": [],
  "consortium_fee": { "rate": 0.05, "amount_mid": 92500 },
  "totals": {
    "should_cost": { "low": 1980000, "mid": 2400000, "high": 2820000 },
    "government_obligation": {
      "low": 2079000,
      "mid": 2520000,
      "high": 2961000
    },
    "performer_share": { "low": 0, "mid": 0, "high": 0 }
  },
  "bid_recommendation": {
    "target_price": 2400000,
    "rationale": "Mid-scenario should-cost; consortium fee passes through; no cost share under path A.",
    "risk_flags": [
      "BLS vintage gap 14 months; aged at 2.5%/yr",
      "CALC+ N=38 — solid pool",
      "NDC participation gate — verify ≥33% work-share before submission"
    ]
  },
  "citations": {
    "statute": [
      "10 USC 4022",
      "10 USC 4022(d)(1)(A)",
      "10 USC 4003",
      "10 USC 3014"
    ],
    "kg_entities": ["sol_001", "requirement_017", "evaluation_factor_003"],
    "kg_chunks": ["chunk_47", "chunk_112"]
  },
  "methodology_notes": [
    "Prototype OT under 10 USC 4022; NDC participation satisfies 10 USC 4022(d)(1)(A) (cost-share required = false).",
    "Milestone payment type per Block 5: all fixed-price. Cost-type ceiling not applicable.",
    "Consortium fee 5% per DIU template; added to government obligation, not performer share."
  ]
}

Read references/relationship_query_patterns.md for the canonical Cypher patterns when you need to surface specific KG relationships (requirement → deliverable → performance_standard chains, evaluation_factor → milestone alignment).

Call write_file with target path artifacts/<workflow_specific_name>.json.

Narrative summary (capture-team-readable)

After the JSON, present a short narrative covering:

  1. Workflow chosen + why (which trigger fired in the selector).
  2. Authority + performer type + cost-share path + WHY this path minimizes our exposure.
  3. Milestone structure (count, payment type, key gates) traced to AO requirements.
  4. Total bid (low/mid/high) + government obligation vs performer out-of-pocket.
  5. Top 3 risk flags (NDC participation gate, BLS data gap, consortium fee assumption, etc.).
  6. Hand-off to proposal-generator for the project-description narrative volume.
  7. Statutory citations.

If the user asked for an artifact, the JSON envelope is ready for renderers (render_xlsx.py produces the bid cost workbook).

What This Skill Does NOT Cover

  • FAR-based contract pricing → use price-to-win. OTs are outside the FAR; this skill cites 10 USC, not FAR 15.404.
  • Proposal prose / win themes / executive summary → use proposal-generator (consumes this skill's JSON envelope as one input).
  • Prime-to-sub statement of work → use subcontractor-sow-builder.
  • FAR clause compliance audit → use compliance-auditor (mostly N/A for OTs anyway).
  • Incumbent award-history research → use competitive-intel.
  • OCONUS travel — GSA Per Diem covers CONUS only; State Dept rates apply for OCONUS (flag and stop).
  • NDC eligibility legal determination — that is an AO determination per 10 USC 3014. We surface the statutory test (no full-CAS DoD contract in prior year) but don't render a binding eligibility opinion.
  • Agreement terms and conditions — legal review required.
  • OCI sweep — use oci-sweeper (relevant when teaming with an NDC sub that has government-customer overlap).