Domain quick reference

  • Traceability runs in two directions and each finds a different defect. Upward: a derived requirement that reaches no parent came from nowhere. Downward: a requirement that must flow down but has no child was accepted and never allocated onward. Neither check substitutes for the other.
  • A top-level requirement is declared, not inferred from a blank parent field. That distinction is the point: if absence of a parent meant "root", every forgotten link would silently become a new root and the upward check would find nothing.
  • The two declarations are cross-checked both ways. A row declared top-level that also names a parent is as much a finding as a derived row with no parent -- the matrix is contradicting itself.
  • A parent that is not itself a row in the matrix is a dangling trace: it looks traced, and it leads out of the document.
  • Parent pointers can close into a cycle, which makes the upward walk non-terminating. Cycles are found explicitly rather than by letting a traversal run away.
  • Allocation is checked against the product tree, not merely for presence. A row allocated to an element that does not exist is untraceable in exactly the way the matrix is meant to prevent.
  • A blank verification method and an unrecognized one are separate findings, raised by separate checks, so one row never double-reports.

Workflow

  1. Confirm every row has a requirement identifier and that identifiers are unique; stop if not, since an ambiguous key makes tracing meaningless.
  2. Check each row for its required DRD fields.
  3. Run the upward trace: top-level rows must name no parent, derived rows must name one, and every named parent must exist.
  4. Run the downward trace: each row expecting flow-down must have at least one child.
  5. Detect parent-pointer cycles and report every requirement on one.
  6. Check each allocation against the product-tree element set, and each verification method against the recognized four.
  7. The matrix is Annex N complete only when the finding list is empty.

Pitfalls

  • Inferring "top level" from a blank parent field, which converts every dropped link into a spurious root and empties the upward check of meaning.
  • Checking the upward trace only. Coverage of the parent requirements is the half that proves nothing was accepted and forgotten.
  • Walking parent pointers without a cycle guard, which hangs on exactly the malformed matrix the audit is supposed to catch.
  • Accepting an allocation string because it is non-empty. A typo names a product element that does not exist and still looks allocated.
  • Reporting a blank verification method twice, once as a missing field and once as an unrecognized method. It is one defect.
  • Reading a high percentage of traced rows as a pass. Annex N coverage is all-or-nothing; the untraced remainder is where the risk sits.

Behavior contract (gate 3)

The row-uniqueness, DRD-field, upward-trace, downward-trace, cycle-detection, allocation and verification-method logic is exercised by the gate 3 contract test: scripts/test_e10_rtm_drd.py against scripts/e10_rtm_drd_logic.py (stdlib unittest, offline). Run: python3 scripts/test_e10_rtm_drd.py

Compliance

  • ECSS standards are freely downloadable (ESA); cite the source and paraphrase per standards-map.yaml.